Officers to be held responsible for delay in commissioning of project: ACS Bharadwaj

June 24, 2022 | BK News Service

 Additional Chief Secretary Finance Department, Vivek Bharadwaj today chaired the 80th meeting of the Board of Directors of Jammu and Kashmir State Power Development Corporation Limited (JKSPDCL) at Civil Secretariat here.
Nitishwar Kumar, Principal Secretary, PDD; Ghanshyam Prasad, Joint Secretary, Ministry of Power, GoI; Dr. Raghav Langer, Secretary, Planning, Development & Monitoring Department; Raja Yaqoob Farooq, Managing Director, JKSPDC; Manoj Tripathi, CPES, I/c HRM, Central Electricity Authority, Ms. Santosh Kumari, Director Finance, JKSPDC; Ms. Raheela Wani, Executive Director (Electric); Jankar Nath, Executive Director (Civil); Sunil Gupta, Company Secretary; besides other officers of the Corporation were present.
During the meeting, the Board of Directors accorded its approval to works programme for the year 2022-23 for an amount of Rs 897.81 crore while the ongoing hydroelectric projects for which funds have been earmarked in the works programme include Parnai HEP, New Karnah HEP.
The New Projects to be taken up for which the funds have been earmarked for the year 2022-23 include Mohra HEP, Lower Kalnai HEP, Agro Solar Pampore and New Ganderbal HEP, the tenders for which have already been floated.
The BoD also accorded approval for the Revenue Budget Estimates for the year 2022-23 and Revised Estimates 2021-22, and an amount of Rs 296.99 crore has been approved under Revenue Budget for the year 2022-23.
The Board also approved to the confirmation/ regularisation of services of eligible probationers viz. Junior Engineers, Geological Assistants and Surveyors (Geology) who have been appointed in 2019,through transparent competitive process.
The Board also accorded approval to price adjustment and its financial implication for EPC contract of Parnai HEP.
The Chairman directed Managing Director to fix the responsibilities of officers for delay in commissioning of the project.
The Board also accorded approval to extension in time of PMC for Dah & Hannu HEPs & PMC for 66 KV transmission line up to 31-12-2022.
The Board also accorded approval for taking up major critical, emergency works and purchase of critical spares, in future from time to time, through OEM strictly in line with the relevant provisions of the GFR 2017 and Manual for procurement 2019.
Principal Secretary, Power Development Department directed that all pending projects be completed within prescribed timelines.

BREAKING NEWS

VIDEO

Twitter

Facebook

80th BoDs meeting of J&K SPDCL approves Rs 897 cr funds


Officers to be held responsible for delay in commissioning of project: ACS Bharadwaj

June 24, 2022 | BK News Service

 Additional Chief Secretary Finance Department, Vivek Bharadwaj today chaired the 80th meeting of the Board of Directors of Jammu and Kashmir State Power Development Corporation Limited (JKSPDCL) at Civil Secretariat here.
Nitishwar Kumar, Principal Secretary, PDD; Ghanshyam Prasad, Joint Secretary, Ministry of Power, GoI; Dr. Raghav Langer, Secretary, Planning, Development & Monitoring Department; Raja Yaqoob Farooq, Managing Director, JKSPDC; Manoj Tripathi, CPES, I/c HRM, Central Electricity Authority, Ms. Santosh Kumari, Director Finance, JKSPDC; Ms. Raheela Wani, Executive Director (Electric); Jankar Nath, Executive Director (Civil); Sunil Gupta, Company Secretary; besides other officers of the Corporation were present.
During the meeting, the Board of Directors accorded its approval to works programme for the year 2022-23 for an amount of Rs 897.81 crore while the ongoing hydroelectric projects for which funds have been earmarked in the works programme include Parnai HEP, New Karnah HEP.
The New Projects to be taken up for which the funds have been earmarked for the year 2022-23 include Mohra HEP, Lower Kalnai HEP, Agro Solar Pampore and New Ganderbal HEP, the tenders for which have already been floated.
The BoD also accorded approval for the Revenue Budget Estimates for the year 2022-23 and Revised Estimates 2021-22, and an amount of Rs 296.99 crore has been approved under Revenue Budget for the year 2022-23.
The Board also approved to the confirmation/ regularisation of services of eligible probationers viz. Junior Engineers, Geological Assistants and Surveyors (Geology) who have been appointed in 2019,through transparent competitive process.
The Board also accorded approval to price adjustment and its financial implication for EPC contract of Parnai HEP.
The Chairman directed Managing Director to fix the responsibilities of officers for delay in commissioning of the project.
The Board also accorded approval to extension in time of PMC for Dah & Hannu HEPs & PMC for 66 KV transmission line up to 31-12-2022.
The Board also accorded approval for taking up major critical, emergency works and purchase of critical spares, in future from time to time, through OEM strictly in line with the relevant provisions of the GFR 2017 and Manual for procurement 2019.
Principal Secretary, Power Development Department directed that all pending projects be completed within prescribed timelines.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.