Chief Secretary reviews progress of USB Rail Link Project

July 05, 2019 | BK ONLINE

 Chief Secretary, B V R Subrahmanyam chaired the Apex Committee meeting to review the progress of the Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project.

Principal Secretary, Home , Financial Commissioner Revenue, J&K, Principal Secretary, Planning Development & Monitoring Department, Administrative Secretaries of the Departments Forest, Ecology & Environment, PDD, Revenue and Tourism, Divisional Commissioner, Kashmir,  Chief Administrative Officer (CAO), USBRL Project, Deputy Commissioner, Srinagar, Deputy Commissioner Budgam and other senior officers and representatives of Railway Authorities were present in the meeting.

Divisional Commissioner, Jammu, Deputy Commissioner, Ramban and Deputy Commissioner, Reasi participated in the meeting through video conferencing. 

CAO, USBRL Project informed the Committee that out of the total 272 Km Rail line between Udhampur and Bramulla, 111 Km stretch between Katra and Banihal remains to be connected.  The stretch has tunnels in 97 Km length and surface Rail line on 14 Kms. He said 67 Km long escape tunnels are also being provided alongside the main tunnels.

Regarding progress of work on the 111Km Katra-Banihal stretch, CAO, USBRL Project informed that 67 Km construction work of the main Tunnels has been completed along with 30 Km of the escape tunnels. He said work on the project is going on smoothly. However, certain issues requiring intervention of the State Government are projected for early resolution.

To expedite the resolution of the issues and completion of the Project, Chief Secretary directed the Railway Authorities to submit on every Monday by 11:00 AM, a weekly progress report along with details about bottlenecks/stoppages, if any, encountered during the previous week to his office, Principal Secretary, Home, Divisional Commissioner, Jammu, IGP Jammu and concerned DCs/SSPs. He asked the Railway Authorities to first seek resolution of the issues with the concerned DCs and Divisional Commissioner, Jammu before referring them to Government.   

In order to put in place a coordination mechanism at the district level for the USBRL Project, State Government will constitute Committees of Deputy Commissioners of Ramban and Reasi with District SPs, concerned Revenue Authorities etc and representatives of IRCON and KRCL as members to review the progress of work every week and discuss resolution of issues, if any.

Timelines were also fixed by Chief Secretary for time bound resolution and completion of the few pending land acquisition, utility shifting and compensation issues in Reasi, Ramban and Budgam districts.

BREAKING NEWS

VIDEO

Twitter

Facebook

Chief Secretary reviews progress of USB Rail Link Project

July 05, 2019 | BK ONLINE

 Chief Secretary, B V R Subrahmanyam chaired the Apex Committee meeting to review the progress of the Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project.

Principal Secretary, Home , Financial Commissioner Revenue, J&K, Principal Secretary, Planning Development & Monitoring Department, Administrative Secretaries of the Departments Forest, Ecology & Environment, PDD, Revenue and Tourism, Divisional Commissioner, Kashmir,  Chief Administrative Officer (CAO), USBRL Project, Deputy Commissioner, Srinagar, Deputy Commissioner Budgam and other senior officers and representatives of Railway Authorities were present in the meeting.

Divisional Commissioner, Jammu, Deputy Commissioner, Ramban and Deputy Commissioner, Reasi participated in the meeting through video conferencing. 

CAO, USBRL Project informed the Committee that out of the total 272 Km Rail line between Udhampur and Bramulla, 111 Km stretch between Katra and Banihal remains to be connected.  The stretch has tunnels in 97 Km length and surface Rail line on 14 Kms. He said 67 Km long escape tunnels are also being provided alongside the main tunnels.

Regarding progress of work on the 111Km Katra-Banihal stretch, CAO, USBRL Project informed that 67 Km construction work of the main Tunnels has been completed along with 30 Km of the escape tunnels. He said work on the project is going on smoothly. However, certain issues requiring intervention of the State Government are projected for early resolution.

To expedite the resolution of the issues and completion of the Project, Chief Secretary directed the Railway Authorities to submit on every Monday by 11:00 AM, a weekly progress report along with details about bottlenecks/stoppages, if any, encountered during the previous week to his office, Principal Secretary, Home, Divisional Commissioner, Jammu, IGP Jammu and concerned DCs/SSPs. He asked the Railway Authorities to first seek resolution of the issues with the concerned DCs and Divisional Commissioner, Jammu before referring them to Government.   

In order to put in place a coordination mechanism at the district level for the USBRL Project, State Government will constitute Committees of Deputy Commissioners of Ramban and Reasi with District SPs, concerned Revenue Authorities etc and representatives of IRCON and KRCL as members to review the progress of work every week and discuss resolution of issues, if any.

Timelines were also fixed by Chief Secretary for time bound resolution and completion of the few pending land acquisition, utility shifting and compensation issues in Reasi, Ramban and Budgam districts.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.