Achieve development goals well in time: DC Asad to official

September 23, 2022 | BK News Service

To review the physical and financial status of the works taken up under District Capex Plan 2022-23 in the District, a meeting of all Sectoral/District Officers was today held under the Chairmanship of the Deputy Commissioner (DC) Srinagar, Mohammad Aijaz Asad here at Meeting Hall of the DC Office Complex.
Besides, Additional District Development Commissioner, Srinagar, Zahoor Ahmad Mir and Chief Planning Officer, Mohammad Yaseen Lone, the meeting was attended by all District/Sectoral Officers, Engineers and other concerned.
At the outset, the Deputy Commissioner took a detailed review of funds released and expenditure under R&B, PHE, Education, Health, RDD PMGSY, NRLM, ICDS and other sectors, besides progress of works taken up under DDC, BDC and PRI grants were also discussed in threadbare.
The DC after taking sector wise review of all works directed the officers to ensure 100 percent expenditure in the set time line by accelerating the pace of the works scheduled for completion during current year. He directed the officers to work in coordinated manner with line departments to achieve development goals well in time keeping in view the limited working season.
The DC also exhorted for mobilizing men and machinery for completing the projects being implemented in the larger interest of the public in stipulated time frame besides urged to ensure productive and fruitful utilization of the available resources.
On the occasion, the DC was apprised that under District Capex, total 523 works were taken up out of which 119 works have been completed while rest of works are going on.
Similarly, under Centrally Sponsored Schemes, 173 works were taken up out of which 44 works were completed. While 17 works taken up under NABARD sector one is completed and remaining works are being carried out in the District.
The DC was further informed that against the approved funds allocation of Funds expenditure has been made so far by achieving 36% percent of the target for year 2022-23. Regarding works under Area Development Plan, ACD informed the meeting forum that 90% works shall be completed by October end.
Similarly, under NRLM, 98 percent, ICDS/Mid day meals over 90% and JJM, 71%, target has been achieved in the District so far.

BREAKING NEWS

VIDEO

Twitter

Facebook

Achieve development goals well in time: DC Asad to official

September 23, 2022 | BK News Service

To review the physical and financial status of the works taken up under District Capex Plan 2022-23 in the District, a meeting of all Sectoral/District Officers was today held under the Chairmanship of the Deputy Commissioner (DC) Srinagar, Mohammad Aijaz Asad here at Meeting Hall of the DC Office Complex.
Besides, Additional District Development Commissioner, Srinagar, Zahoor Ahmad Mir and Chief Planning Officer, Mohammad Yaseen Lone, the meeting was attended by all District/Sectoral Officers, Engineers and other concerned.
At the outset, the Deputy Commissioner took a detailed review of funds released and expenditure under R&B, PHE, Education, Health, RDD PMGSY, NRLM, ICDS and other sectors, besides progress of works taken up under DDC, BDC and PRI grants were also discussed in threadbare.
The DC after taking sector wise review of all works directed the officers to ensure 100 percent expenditure in the set time line by accelerating the pace of the works scheduled for completion during current year. He directed the officers to work in coordinated manner with line departments to achieve development goals well in time keeping in view the limited working season.
The DC also exhorted for mobilizing men and machinery for completing the projects being implemented in the larger interest of the public in stipulated time frame besides urged to ensure productive and fruitful utilization of the available resources.
On the occasion, the DC was apprised that under District Capex, total 523 works were taken up out of which 119 works have been completed while rest of works are going on.
Similarly, under Centrally Sponsored Schemes, 173 works were taken up out of which 44 works were completed. While 17 works taken up under NABARD sector one is completed and remaining works are being carried out in the District.
The DC was further informed that against the approved funds allocation of Funds expenditure has been made so far by achieving 36% percent of the target for year 2022-23. Regarding works under Area Development Plan, ACD informed the meeting forum that 90% works shall be completed by October end.
Similarly, under NRLM, 98 percent, ICDS/Mid day meals over 90% and JJM, 71%, target has been achieved in the District so far.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.