Secretary RDD reviews PMAY-G progress

97% houses completed, directs completion of remaining by April 2026

March 15, 2026 | BK News Service

JAMMU, MARCH 14: Secretary, Rural Development Department (RDD) and Panchayati Raj, Mohammad Aijaz Asad on Saturday chaired a high-level meeting to review the progress of Pradhan Mantri Awas Yojana–Gramin (PMAY-G) across Jammu and Kashmir.
During the meeting, a detailed district-wise review of the scheme was undertaken with particular focus on completion of the pending houses. It was informed that 3,23,299 houses have already been completed, achieving an overall progress of 97 percent under the scheme.
The Secretary noted that 3447 houses have been completed from the last 2 months and directed officers to further accelerate the pace of work so that the remaining 11,340 houses are completed at the earliest.
Speaking on the occasion, Aijaz Asad said that the current phase of PMAY-G is nearing completion and a new phase of the scheme is set to begin, therefore all works sanctioned under the existing phase must be completed without delay. He asked officers to work with seriousness and accountability to achieve the targets.
He directed Assistant Commissioners Development (ACDs) and Block Development Officers (BDOs) to track each individual case and ensure that no sanctioned house remains incomplete. He further instructed that any technical or administrative bottlenecks hindering the progress of works should be resolved immediately.
The Secretary emphasized that all pending works must be completed by April 15, 2026, stressing that officers should make every possible effort, even if it requires working round the clock, as houses left incomplete under the previous phase will not be taken up once the new phase begins.
Aijaz also directed the Director Rural Development Jammu and Director Rural Development Kashmir to hold weekly review meetings and keep the department informed about the progress achieved.
He further stressed the need for early release of pending installments to beneficiaries, directing ACDs to conduct block-wise reviews in this regard.
Highlighting the importance of the recent survey conducted prior to the launch of the new phase, Aijaz Asad said that although the survey has been carried out using AI-based technology, it will still be reviewed at the Deputy Commissioner level to ensure that no eligible household is left out of the scheme.
Among others, the meeting was attended by Director Rural Development Kashmir Shabir Hussain Bhat, Director Rural Development Jammu Shehnaz Akhtar, Joint Director Planning Kamal Kumar Sharma, besides ACDs and BDOs.

BREAKING NEWS

VIDEO

Twitter

Facebook

Secretary RDD reviews PMAY-G progress

97% houses completed, directs completion of remaining by April 2026

March 15, 2026 | BK News Service

JAMMU, MARCH 14: Secretary, Rural Development Department (RDD) and Panchayati Raj, Mohammad Aijaz Asad on Saturday chaired a high-level meeting to review the progress of Pradhan Mantri Awas Yojana–Gramin (PMAY-G) across Jammu and Kashmir.
During the meeting, a detailed district-wise review of the scheme was undertaken with particular focus on completion of the pending houses. It was informed that 3,23,299 houses have already been completed, achieving an overall progress of 97 percent under the scheme.
The Secretary noted that 3447 houses have been completed from the last 2 months and directed officers to further accelerate the pace of work so that the remaining 11,340 houses are completed at the earliest.
Speaking on the occasion, Aijaz Asad said that the current phase of PMAY-G is nearing completion and a new phase of the scheme is set to begin, therefore all works sanctioned under the existing phase must be completed without delay. He asked officers to work with seriousness and accountability to achieve the targets.
He directed Assistant Commissioners Development (ACDs) and Block Development Officers (BDOs) to track each individual case and ensure that no sanctioned house remains incomplete. He further instructed that any technical or administrative bottlenecks hindering the progress of works should be resolved immediately.
The Secretary emphasized that all pending works must be completed by April 15, 2026, stressing that officers should make every possible effort, even if it requires working round the clock, as houses left incomplete under the previous phase will not be taken up once the new phase begins.
Aijaz also directed the Director Rural Development Jammu and Director Rural Development Kashmir to hold weekly review meetings and keep the department informed about the progress achieved.
He further stressed the need for early release of pending installments to beneficiaries, directing ACDs to conduct block-wise reviews in this regard.
Highlighting the importance of the recent survey conducted prior to the launch of the new phase, Aijaz Asad said that although the survey has been carried out using AI-based technology, it will still be reviewed at the Deputy Commissioner level to ensure that no eligible household is left out of the scheme.
Among others, the meeting was attended by Director Rural Development Kashmir Shabir Hussain Bhat, Director Rural Development Jammu Shehnaz Akhtar, Joint Director Planning Kamal Kumar Sharma, besides ACDs and BDOs.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.