‘Sonamarg Green belt left unprotected’

November 20, 2026 | BK NEWS SERVICE

Sonamarg, Nov 19: An 800-metre fencing project aimed at protecting the green belt in the tourist resort of Sonamarg has remained stalled for the past four months, leaving the ecologically sensitive area exposed and triggering resentment among locals.

Sanctioned under the CAPEX Budget 2025-26 at an estimated cost of ₹3.5 crore, the project was intended to safeguard the green belt and preserve the natural surroundings of the popular tourist destination.
The Roads and Buildings Department had invited tenders after approval of the project, and work was subsequently started. However, execution came to an abrupt halt after a few months, with no clarity on when it would resume.
The suspension has raised concerns among locals, particularly as the fencing earlier installed by the Sonamarg Development Authority was removed during the execution of the new project.
With the old barrier removed and the replacement fencing incomplete, horses are now moving freely inside the green belt, raising fears of damage to its vegetation and natural environment.
Locals have questioned the decision to dismantle the existing fencing before completing the replacement structure. They have urged the Sonamarg Development Authority to reinstall the old barrier immediately and protect the green belt until the new project is completed.
They said leaving the area unprotected defeats the very purpose of the project and could undermine efforts to preserve Sonamarg's natural beauty.
The residents have sought an explanation from the concerned authorities over the prolonged delay, besides demanding the immediate resumption of work and restoration of the earlier fencing as an interim protective measure.

BREAKING NEWS

VIDEO

Twitter

Facebook

‘Sonamarg Green belt left unprotected’

November 20, 2026 | BK NEWS SERVICE

Sonamarg, Nov 19: An 800-metre fencing project aimed at protecting the green belt in the tourist resort of Sonamarg has remained stalled for the past four months, leaving the ecologically sensitive area exposed and triggering resentment among locals.

Sanctioned under the CAPEX Budget 2025-26 at an estimated cost of ₹3.5 crore, the project was intended to safeguard the green belt and preserve the natural surroundings of the popular tourist destination.
The Roads and Buildings Department had invited tenders after approval of the project, and work was subsequently started. However, execution came to an abrupt halt after a few months, with no clarity on when it would resume.
The suspension has raised concerns among locals, particularly as the fencing earlier installed by the Sonamarg Development Authority was removed during the execution of the new project.
With the old barrier removed and the replacement fencing incomplete, horses are now moving freely inside the green belt, raising fears of damage to its vegetation and natural environment.
Locals have questioned the decision to dismantle the existing fencing before completing the replacement structure. They have urged the Sonamarg Development Authority to reinstall the old barrier immediately and protect the green belt until the new project is completed.
They said leaving the area unprotected defeats the very purpose of the project and could undermine efforts to preserve Sonamarg's natural beauty.
The residents have sought an explanation from the concerned authorities over the prolonged delay, besides demanding the immediate resumption of work and restoration of the earlier fencing as an interim protective measure.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.