BREAKING NEWS

10-20-2026     3 رجب 1440

J&K Govt may cancel Emaar lease over project delay

October 20, 2026 | BK NEWS SERVICE

Jammu, Oct 19: The Jammu and Kashmir government is considering cancelling the land lease granted to UAE-based real estate major Emaar Group after its proposed multipurpose mall and IT park in Jammu failed to move beyond the foundation stone laid three years ago.
An official said the agreement required the company to complete construction within three years of taking possession of the land, with provisions for penalties and lease cancellation in case of non-compliance.
“The company has not started construction, and the government is not inclined to extend the lease,” the official said.
Under the agreement, the government could have granted a one-year extension if the company had shown progress towards starting the project. However, officials indicated that no such relief was likely in view of the continued delay.
The government had leased around 24 kanals of land to Emaar for 40 years to develop a G 6 multipurpose tower at an estimated cost of ₹125 crore.
Lieutenant Governor Manoj Sinha laid the foundation stone for the project at the Exhibition Ground near Press Club Jammu on March 19, 2023, in the presence of BJP national general secretary Kailash Vijayvargiya.
Emaar, a UAE-based real estate developer, is known for landmark projects including the Burj Khalifa and Dubai Mall. The prolonged delay in the Jammu project has raised questions over the implementation of the proposed investment.

BREAKING NEWS

VIDEO

Twitter

Facebook

J&K Govt may cancel Emaar lease over project delay

October 20, 2026 | BK NEWS SERVICE

Jammu, Oct 19: The Jammu and Kashmir government is considering cancelling the land lease granted to UAE-based real estate major Emaar Group after its proposed multipurpose mall and IT park in Jammu failed to move beyond the foundation stone laid three years ago.
An official said the agreement required the company to complete construction within three years of taking possession of the land, with provisions for penalties and lease cancellation in case of non-compliance.
“The company has not started construction, and the government is not inclined to extend the lease,” the official said.
Under the agreement, the government could have granted a one-year extension if the company had shown progress towards starting the project. However, officials indicated that no such relief was likely in view of the continued delay.
The government had leased around 24 kanals of land to Emaar for 40 years to develop a G 6 multipurpose tower at an estimated cost of ₹125 crore.
Lieutenant Governor Manoj Sinha laid the foundation stone for the project at the Exhibition Ground near Press Club Jammu on March 19, 2023, in the presence of BJP national general secretary Kailash Vijayvargiya.
Emaar, a UAE-based real estate developer, is known for landmark projects including the Burj Khalifa and Dubai Mall. The prolonged delay in the Jammu project has raised questions over the implementation of the proposed investment.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.