CS reviews hydropower push, sets deadlines for key projects

July 05, 2025 | BK News Service

Chief Secretary Atal Dulloo chaired a high-level meeting to review and accelerate the development of hydropower projects in Jammu & Kashmir, emphasizing their critical role in achieving sustainable economic growth and energy security.
Senior officials from the Power Development Department, Finance, Disaster Management, and Deputy Commissioners participated, with a clear directive from the Chief Secretary to complete all projects within set timelines.
“Hydropower is the mainstay of our economy. Timely execution is non-negotiable,” Dulloo asserted, highlighting the sector’s potential to generate employment and boost industrial development in the Union Territory.
A key focus of the meeting was ensuring that rehabilitation and resettlement (R&R) plans for affected communities include market-driven skill training, enabling local youth to benefit directly from ongoing projects. The Chief Secretary also called for prioritizing public demands through the Local Area Development component to ensure inclusive benefits.
Principal Secretary PDD Rajesh Prasad informed the meeting that J&K has a hydropower potential of 18,000 MW, with 15,000 MW already identified. Of this, 3,540.15 MW has been tapped so far, and 7,768 MW is under various stages of implementation, including 3,063.5 MW under construction.
Major projects under progress include:
Parnai HEP (37.5 MW): 64% complete, to be commissioned by Dec 2027
Karnah HEP (12 MW): 74.75% complete, expected by Nov 2025
Pakaldul HEP (1000 MW): 70% progress, target Dec 2026
Kiru HEP (624 MW): 64% complete, also due Dec 2026
Kwar HEP (540 MW): 22.15% progress, due March 2028
Ratle HEP (850 MW): Excavation work nearing completion, set for Aug 2029
Upcoming projects include Sawalkote (1856 MW), Kirthai I & II, Dulhasti-II, Uri-I Stage II, Bursar, and Ujh Multipurpose projects.
JKSPDC is also expanding into solar energy with a 10 MW agro-solar project at Pampore and floating solar projects on the Lower Jehlum and Baglihar reservoirs.
The Chief Secretary assured fast-track approvals and resolution of project bottlenecks, reiterating the government’s commitment to making J&K a power-surplus region.

BREAKING NEWS

VIDEO

Twitter

Facebook

CS reviews hydropower push, sets deadlines for key projects

July 05, 2025 | BK News Service

Chief Secretary Atal Dulloo chaired a high-level meeting to review and accelerate the development of hydropower projects in Jammu & Kashmir, emphasizing their critical role in achieving sustainable economic growth and energy security.
Senior officials from the Power Development Department, Finance, Disaster Management, and Deputy Commissioners participated, with a clear directive from the Chief Secretary to complete all projects within set timelines.
“Hydropower is the mainstay of our economy. Timely execution is non-negotiable,” Dulloo asserted, highlighting the sector’s potential to generate employment and boost industrial development in the Union Territory.
A key focus of the meeting was ensuring that rehabilitation and resettlement (R&R) plans for affected communities include market-driven skill training, enabling local youth to benefit directly from ongoing projects. The Chief Secretary also called for prioritizing public demands through the Local Area Development component to ensure inclusive benefits.
Principal Secretary PDD Rajesh Prasad informed the meeting that J&K has a hydropower potential of 18,000 MW, with 15,000 MW already identified. Of this, 3,540.15 MW has been tapped so far, and 7,768 MW is under various stages of implementation, including 3,063.5 MW under construction.
Major projects under progress include:
Parnai HEP (37.5 MW): 64% complete, to be commissioned by Dec 2027
Karnah HEP (12 MW): 74.75% complete, expected by Nov 2025
Pakaldul HEP (1000 MW): 70% progress, target Dec 2026
Kiru HEP (624 MW): 64% complete, also due Dec 2026
Kwar HEP (540 MW): 22.15% progress, due March 2028
Ratle HEP (850 MW): Excavation work nearing completion, set for Aug 2029
Upcoming projects include Sawalkote (1856 MW), Kirthai I & II, Dulhasti-II, Uri-I Stage II, Bursar, and Ujh Multipurpose projects.
JKSPDC is also expanding into solar energy with a 10 MW agro-solar project at Pampore and floating solar projects on the Lower Jehlum and Baglihar reservoirs.
The Chief Secretary assured fast-track approvals and resolution of project bottlenecks, reiterating the government’s commitment to making J&K a power-surplus region.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.