Rs 41.78 cr Maitra bridge over Chenab to be completed by August 2026: Dy CM

March 12, 2025 | BK NEWS SERVICE

Deputy Chief Minister, Surinder Choudhary, today informed the House that the Rs. 41.78 crore Maitra Ramban bridge over river Chenab shall be completed by August 2026.

The Deputy Chief Minister was replying to a question raised by Arjun Singh Raju in the Legislative Assembly.

He said that men and machinery is being mobilized and work has been accelerated for timely completion of the project. He informed the House that execution of bridge over river Chenab at Maitra Ramban, sanctioned under CRIF, was delayed, as NHAI did not allow intersection of this bridge with 4-lane Ramban flyover carrying fast moving motorized traffic.

The Deputy Chief Minister said that the bridge has now been planned to intersect with old NH, due to which the height of the bridge is being raised by 8.5 m and span extended by 30 m to 300 m.

He added that foundation of both the abutments has been completed while as Gantry on Maitra side stands installed and casting is in progress. He said that on the Ramban side, pier headwork is under progress and work of casting of segment/deck slab has been started.

The Deputy Chief Minister said that the project has picked up pace as the contractor has mobilized men and machinery in strength. He added that against a sanctioned cost of Rs. 41.78 crore, till date, an amount of Rs. 21.10 crore has been released in favour of the contractor and the bridge is expected to be completed by August 2026.

BREAKING NEWS

VIDEO

Twitter

Facebook

Rs 41.78 cr Maitra bridge over Chenab to be completed by August 2026: Dy CM

March 12, 2025 | BK NEWS SERVICE

Deputy Chief Minister, Surinder Choudhary, today informed the House that the Rs. 41.78 crore Maitra Ramban bridge over river Chenab shall be completed by August 2026.

The Deputy Chief Minister was replying to a question raised by Arjun Singh Raju in the Legislative Assembly.

He said that men and machinery is being mobilized and work has been accelerated for timely completion of the project. He informed the House that execution of bridge over river Chenab at Maitra Ramban, sanctioned under CRIF, was delayed, as NHAI did not allow intersection of this bridge with 4-lane Ramban flyover carrying fast moving motorized traffic.

The Deputy Chief Minister said that the bridge has now been planned to intersect with old NH, due to which the height of the bridge is being raised by 8.5 m and span extended by 30 m to 300 m.

He added that foundation of both the abutments has been completed while as Gantry on Maitra side stands installed and casting is in progress. He said that on the Ramban side, pier headwork is under progress and work of casting of segment/deck slab has been started.

The Deputy Chief Minister said that the project has picked up pace as the contractor has mobilized men and machinery in strength. He added that against a sanctioned cost of Rs. 41.78 crore, till date, an amount of Rs. 21.10 crore has been released in favour of the contractor and the bridge is expected to be completed by August 2026.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.