J&K Completes 46% of Jal Jeevan Mission Works, Contractor Dues Reach ₹1,360 Crore

September 04, 2026 | BK NEWS SERVICE

Srinagar, Sep 4: Only 46 percent of the physical works planned under the Jal Jeevan Mission (JJM) in Jammu and Kashmir have been completed, while contractor payments amounting to ₹1,360 crore remain pending, according to a report of a Parliamentary Standing Committee.

The findings were highlighted by the Department-related Parliamentary Standing Committee on Home Affairs in its report examining administrative governance, socio-economic development and the security situation in Jammu and Kashmir and Ladakh.

The committee noted that implementation of the Jal Jeevan Mission in J&K had experienced delays, with physical execution progressing slower than required to complete the targeted works.

According to the report, just 46 percent of the planned physical works had been completed, while ₹1,360 crore in payments to contractors remained outstanding.

The committee expressed concern over the slow pace of implementation and recommended that the authorities accelerate the execution of pending projects and ensure timely release of funds.

The Jal Jeevan Mission aims to provide functional household tap connections to rural families and develop the infrastructure needed for a dependable supply of drinking water.

The panel stressed the need for better coordination among departments to remove administrative and financial bottlenecks and ensure that beneficiaries receive functional tap-water connections.

The large amount of pending contractor payments could also affect the pace of ongoing infrastructure works, particularly projects dependent on regular cash flow for construction and related activities.

The committee called for closer monitoring of the mission and faster resolution of administrative and financial issues delaying its implementation in Jammu and Kashmir.

The findings come as J&K continues to expand rural drinking-water infrastructure under the centrally sponsored Jal Jeevan Mission.

J&K Completes 46% of Jal Jeevan Mission Works, Contractor Dues Reach ₹1,360 Crore

September 04, 2026 | BK NEWS SERVICE

Srinagar, Sep 4: Only 46 percent of the physical works planned under the Jal Jeevan Mission (JJM) in Jammu and Kashmir have been completed, while contractor payments amounting to ₹1,360 crore remain pending, according to a report of a Parliamentary Standing Committee.

The findings were highlighted by the Department-related Parliamentary Standing Committee on Home Affairs in its report examining administrative governance, socio-economic development and the security situation in Jammu and Kashmir and Ladakh.

The committee noted that implementation of the Jal Jeevan Mission in J&K had experienced delays, with physical execution progressing slower than required to complete the targeted works.

According to the report, just 46 percent of the planned physical works had been completed, while ₹1,360 crore in payments to contractors remained outstanding.

The committee expressed concern over the slow pace of implementation and recommended that the authorities accelerate the execution of pending projects and ensure timely release of funds.

The Jal Jeevan Mission aims to provide functional household tap connections to rural families and develop the infrastructure needed for a dependable supply of drinking water.

The panel stressed the need for better coordination among departments to remove administrative and financial bottlenecks and ensure that beneficiaries receive functional tap-water connections.

The large amount of pending contractor payments could also affect the pace of ongoing infrastructure works, particularly projects dependent on regular cash flow for construction and related activities.

The committee called for closer monitoring of the mission and faster resolution of administrative and financial issues delaying its implementation in Jammu and Kashmir.

The findings come as J&K continues to expand rural drinking-water infrastructure under the centrally sponsored Jal Jeevan Mission.


  • Address: R.C 2 Quarters Press Enclave Near Pratap Park, Srinagar 190001.
  • Phone: 0194-2451076 , +91-941-940-0056 , +91-962-292-4716
  • Email: brighterkmr@gmail.com
Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Sangermal offset Printing Press Rangreth ( Budgam)
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076
Mobile No’s 9419400056, 9622924716 ,7006086442
Postal Regd No: SK/135/2010-2019
POST BOX NO: 1001
Administrative Office: R.C 2 Quarters Press Enclave Near Pratap Park ( Srinagar -190001)

© Copyright 2023 brighterkashmir.com All Rights Reserved. Quantum Technologies

Owner, Printer, Publisher, Editor: Farooq Ahmad Wani
Legal Advisor: M.J. Hubi
Printed at: Abid Enterprizes, Zainkote Srinagar
Published from: Gulshanabad Chraresharief Budgam
RNI No.: JKENG/2010/33802
Office No’s: 0194-2451076, 9622924716 , 9419400056
Postal Regd No: SK/135/2010-2019
Administrative Office: Abi Guzer Srinagar

© Copyright 2018 brighterkashmir.com All Rights Reserved.